Table of Contents
Project Documents.
1.1 WBS.
1.2 WBS dictionary.
1.3 Activity List
Bibliography.
The project document is generally based on the project schedule where the activities of the project have been mentioned. This document is included with the cost of every activities and the duration of these activities which have been highlighted in this project. In addition, this document will mention the activity description and time schedule within that the activities need to be completed. Moreover, the project document will include that estimated cost which has been calculated for every activity. In addition, the project document will calculate the estimated cost based on the activities and it will measure the extra cost if that will be needed for the project.
The WBS is needed for the project scope and the objective of the project. The structure will provide the schedule and it will measure the time schedule of the project. It will calculate around which time the project will be completed. In addition, this structure will help to identify the task activities and the task which will take place one by one.
WBS stands for work breakdown structure and it ensures the identification of improved work packages. The process ensures the identification of the key activities aligning with the process for managing the activity levels.
First Level |
Second level |
Third level |
Fourth Level |
Description |
1 |
SILT Containment |
|||
1.1 |
Contour & SITE SURVEY |
|||
2 |
BUILDING DESIGN |
|||
2.1 |
COLOUR CONSULTANT |
|||
2.2 |
ENERGY EFFICIENCY CERTIFICATE |
|||
3 |
ENGINEER |
|||
3.1 |
CONTRACTORS INSURANCE |
|||
3.1.1 |
Contractors Insurance for building |
|||
3.1.2 |
HOME WARRANTY INSURANCE |
|||
3.1.2.1 |
SAFETY AND HEALTH INSURANCE |
|||
4 |
4 |
COUNCIL FEES AND PERMITS |
||
5 |
5 |
TOILET HIRE |
||
5.1 |
HIRE |
|||
6 |
6 |
SITE EXCAVATION |
||
7 |
7 |
RETAINING WALLS |
||
8 |
8 |
SETTING OUT SURVEYOR HOUSE |
||
9 |
9 |
SANDUP AND DETAILED EXCAVATION |
||
9.1 |
CONCRETE PUMP |
|||
10 |
10 |
FOOTINGS HARDWARE |
||
11 |
11 |
FOOTINGS CONCRETE |
||
12 |
12 |
FOOTING LABOUR |
||
13 |
13 |
ELECTRICIAN SITE WORKS |
||
14 |
14 |
PLUMBER DRAINAGE |
||
15 |
15 |
BEDDING SAND |
||
15.1 |
SEDIMENT GRAVEL |
|||
16 |
16 |
TERMITE TREATMENT |
||
16.1 |
SPOIL REMOVAL |
|||
17 |
17 |
SLAB HARDWARE |
||
18 |
18 |
SLAB CONCRETE |
||
19 |
19 |
SLAB LABOUR |
||
20 |
20 |
BACKFILL POWER TRENCH |
||
21 |
21 |
STICK FRAME IN LOWER FLOOR |
||
21.1 |
FLOOR MATERIALS IN UPPER FLOOR |
|||
22 |
22 |
STICK FRAME IN UPPER FLOOR |
||
23 |
23 |
T&G FLOORING |
||
24 |
24 |
FRAME HARDWARE |
||
24.1 |
CARPENTER BUILDING |
|||
25 |
25 |
ROOF TRUSSES |
||
26 |
26 |
CARPENTER FRAME |
||
27 |
27 |
GUTTERS AND FASCIA |
||
27.1 |
DECK GUARD RAIL |
|||
28 |
28 |
CRANE HIRE |
||
29 |
29 |
ROOF COVERING |
||
30 |
30 |
WATERPROOFING |
||
31 |
31 |
SPA BATHS AND BATHING |
||
32 |
32 |
PLUMBERS ROUGH IN |
||
33 |
33 |
ELECTRICAN |
||
33.1 |
GAS CONNECTION |
|||
34 |
34 |
ALUMINIUM WINDOWS |
||
35 |
35 |
DOOR LOCK EXTERNAL |
||
36 |
36 |
JAMBS AND EXTERNAL DOORS |
||
36.1 |
SITE CLEAN |
|||
37 |
37 |
HARDWARE LOCK AND SOFFIT SHEETS |
||
38 |
38 |
SOFFITS AND CARPENTER LOCK |
||
39 |
39 |
SCAFFOLDING |
||
40 |
40 |
BRICKS |
||
41 |
41 |
BRICK HARDWARE |
||
42 |
42 |
BRICKLAYER |
||
42.1 |
MASONARY ARTICULATION |
|||
43 |
43 |
INSULATION- WALL BATTS |
||
44 |
44 |
CEILING LININGS AND WALL |
||
45 |
45 |
GARAGE DOORS |
||
46 |
46 |
DOOR KNOBS AND HARDWARE FINISHING |
||
47 |
47 |
NTERNAL DOOR AND FINISHING TIMBER |
||
48 |
48 |
INTERNAL STAIRS |
||
49 |
49 |
CABINETMAKER |
||
50 |
50 |
CARPENTER FIXOUT |
||
51 |
51 |
WALL APPLICATIONS |
||
52 |
52 |
CERAMIC TILES |
||
52.1 |
CERAMIC TILES IN NON-WET AREA |
|||
53 |
53 |
CERAMIC TILER |
||
54 |
54 |
SHOWER SCREENS |
||
55 |
55 |
SANITARY WARE |
||
55.1 |
PLUMBERS FIT OFF |
|||
56 |
56 |
PAINTER |
||
57 |
57 |
WHITE GOODS |
||
58 |
58 |
LIGHT FITTINGS |
||
59 |
59 |
CURTAINS AND SHUTTER |
||
60 |
60 |
TV ANTENA |
||
61 |
61 |
POLISHING AND FLOOR SANDING |
||
62 |
62 |
METAL FENCING |
||
63 |
63 |
CONCRETOR EXTERNA |
||
63.1 |
CONCRETE HARDWARE EXTERNA |
|||
64 |
64 |
EXTERNAL CONCRETE |
||
65 |
65 |
CONCRETE SAND EXTERNAL |
||
66 |
66 |
CONCRETE MACHINE HIRING |
||
67 |
67 |
FINAL FIX CARPENTER |
||
68 |
68 |
HOT WATERING SYSTEM |
||
69 |
69 |
SECURITY SCREENS |
||
70 |
70 |
INSULATION |
||
71 |
71 |
HOUSE CLEAN |
||
72 |
72 |
FINAL SITE CLEANING |
||
73 |
73 |
LANDSCAPE |
||
73.1 |
||||
74 |
74 |
GARDEN EDGING |
||
75 |
75 |
FLOOR COVERINGS |
||
76 |
76 |
FENCING |
||
77 |
77 |
CLOTHS HOISTS |
||
78 |
78 |
ESTIMATING |
||
79 |
79 |
THEFT AND CONTINGENCY |
||
80 |
80 |
WINDOW SERVICE |
||
81 |
81 |
PLUMBING APPROVAL |
||
82 |
82 |
MAINTENANCE |
||
83 |
83 |
POWER USAGE |
From the above table it can be found that the WBS dictionary has included the task and subtask of the project and every task schedule which will take place for the project. Here, the dictionary will also the principle task and the sub task that will be mentioned one by one where it will be evaluated which subtask is allocated in which main task.
Task Name |
Duration |
Start |
Finish |
Predecessors |
Cost |
SILT Containment |
3 days |
Tue 9/1/20 |
Thu 9/3/20 |
$1,930.00 |
|
Contour & SITE SURVEY |
3 days |
Tue 9/1/20 |
Thu 9/3/20 |
$1,710.00 |
|
BUILDING DESIGN |
3 days |
Tue 9/1/20 |
Thu 9/3/20 |
$4,850.00 |
|
COLOUR CONSULTANT |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$500.00 |
|
ENERGY EFFICIENCY CERTIFICATE |
1 day |
Thu 9/3/20 |
Thu 9/3/20 |
$850.00 |
|
ENGINEER |
5 days |
Fri 9/4/20 |
Thu 9/10/20 |
2 |
$9,042.50 |
CONTRACTORS INSURANCE |
5 days |
Fri 9/4/20 |
Thu 9/10/20 |
$7,137.50 |
|
Contractors Insurance for building |
1 day |
Fri 9/4/20 |
Fri 9/4/20 |
$0.00 |
|
HOME WARRANTY INSURANCE |
5 days |
Fri 9/4/20 |
Thu 9/10/20 |
$3,287.50 |
|
1 day |
Fri 9/4/20 |
Fri 9/4/20 |
$0.00 |
||
SAFETY AND HEALTH INSURANCE |
3 days |
Tue 9/8/20 |
Thu 9/10/20 |
$1,347.50 |
|
COUNCIL FEES AND PERMITS |
5 days |
Mon 9/7/20 |
Fri 9/11/20 |
$3,649.64 |
|
TOILET HIRE |
2 days |
Mon 9/7/20 |
Tue 9/8/20 |
$1,160.00 |
|
HIRE |
2 days |
Mon 9/7/20 |
Tue 9/8/20 |
$200.00 |
|
SITE EXCAVATION |
2 days |
Mon 9/7/20 |
Tue 9/8/20 |
$650.00 |
|
RETAINING WALLS |
3 days |
Mon 9/7/20 |
Wed 9/9/20 |
$5,204.84 |
|
SETTING OUT SURVEYOR HOUSE |
1 day |
Tue 9/8/20 |
Tue 9/8/20 |
$475.00 |
|
SANDUP AND DETAILED EXCAVATION |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,578.55 |
|
CONCRETE PUMP |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,200.00 |
|
FOOTINGS HARDWARE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,485.99 |
|
FOOTINGS CONCRETE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$3,191.31 |
|
FOOTING LABOUR |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,572.00 |
|
ELECTRICIAN SITE WORKS |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,001.50 |
|
PLUMBER DRAINAGE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$5,498.00 |
|
BEDDING SAND |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,425.00 |
|
SEDIMENT GRAVEL |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$300.00 |
|
TERMITE TREATMENT |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,602.20 |
|
SPOIL REMOVAL |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$200.00 |
|
SLAB HARDWARE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,834.93 |
|
SLAB CONCRETE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$4,703.05 |
|
SLAB LABOUR |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$3,343.65 |
|
BACKFILL POWER TRENCH |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$101.00 |
|
STICK FRAME IN LOWER FLOOR |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$15,700.07 |
|
FLOOR MATERIALS IN UPPER FLOOR |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$6,724.65 |
|
STICK FRAME IN UPPER FLOOR |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$3,505.12 |
|
T&G FLOORING |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,939.39 |
|
FRAME HARDWARE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,524.99 |
|
CARPENTER BUILDING |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$329.76 |
|
ROOF TRUSSES |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$8,831.05 |
|
CARPENTER FRAME |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$8,696.95 |
|
GUTTERS AND FASCIA |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$4,283.45 |
|
DECK GUARD RAIL |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,790.25 |
|
CRANE HIRE |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$450.00 |
|
ROOF COVERING |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$12,455.85 |
|
WATERPROOFING |
1 day? |
Tue 9/1/20 |
Tue 9/1/20 |
$1,222.00 |
|
SPA BATHS AND BATHING |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$239.00 |
|
PLUMBERS ROUGH IN |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$3,089.90 |
|
ELECTRICAN |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$6,638.05 |
|
GAS CONNECTION |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,875.00 |
|
ALUMINIUM WINDOWS |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$8,034.65 |
|
DOOR LOCK EXTERNAL |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$339.30 |
|
JAMBS AND EXTERNAL DOORS |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,695.50 |
|
SITE CLEAN |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$800.00 |
|
HARDWARE LOCK AND SOFFIT SHEETS |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,046.41 |
|
SOFFITS AND CARPENTER LOCK |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,914.30 |
|
SCAFFOLDING |
3 days |
Wed 9/9/20 |
Fri 9/11/20 |
$6,200.00 |
|
BRICKS |
3 days |
Wed 9/9/20 |
Fri 9/11/20 |
$3,682.20 |
|
BRICK HARDWARE |
1 day |
Mon 9/14/20 |
Mon 9/14/20 |
57 |
$505.40 |
BRICKLAYER |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$11,769.70 |
|
MASONARY ARTICULATION |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$181.60 |
|
INSULATION- WALL BATTS |
1 day |
Wed 9/9/20 |
Wed 9/9/20 |
$654.91 |
|
CEILING LININGS AND WALL |
1 day |
Thu 9/10/20 |
Thu 9/10/20 |
61 |
$13,084.14 |
GARAGE DOORS |
1 day |
Wed 9/9/20 |
Wed 9/9/20 |
$2,094.46 |
|
DOOR KNOBS AND HARDWARE FINISHING |
2 days |
Thu 9/3/20 |
Fri 9/4/20 |
$729.80 |
|
INTERNAL DOOR AND FINISHING TIMBER |
2 days |
Thu 9/3/20 |
Fri 9/4/20 |
$2,188.80 |
|
INTERNAL STAIRS |
4 days |
Fri 9/4/20 |
Wed 9/9/20 |
1 |
$2,010.00 |
CABINETMAKER |
4 days |
Mon 9/7/20 |
Thu 9/10/20 |
65 |
$9,129.56 |
CARPENTER FIXOUT |
4 days |
Mon 9/7/20 |
Thu 9/10/20 |
64 |
$2,694.50 |
WALL APPLICATIONS |
4 days |
Mon 9/7/20 |
Thu 9/10/20 |
3 |
$960.00 |
CERAMIC TILES |
2 days |
Fri 9/11/20 |
Mon 9/14/20 |
7 |
$2,744.33 |
CERAMIC TILES IN NON WET AREA |
2 days |
Fri 9/11/20 |
Mon 9/14/20 |
69 |
$1,566.91 |
CERAMIC TILER |
4 days |
Tue 9/8/20 |
Fri 9/11/20 |
$4,847.90 |
|
JOINT TILE SEALING |
4 days |
Tue 9/8/20 |
Fri 9/11/20 |
$300.00 |
|
SHOWER SCREENS |
4 days |
Tue 9/8/20 |
Fri 9/11/20 |
$1,779.37 |
|
SANITARY WARE |
1 day? |
Fri 9/11/20 |
Fri 9/11/20 |
$4,167.23 |
|
PLUMBERS FIT OFF |
1 day? |
Fri 9/11/20 |
Fri 9/11/20 |
$3,101.23 |
|
PAINTER |
5 days |
Fri 9/11/20 |
Thu 9/17/20 |
9 |
$8,101.48 |
WHITE GOODS |
5 days |
Mon 9/7/20 |
Fri 9/11/20 |
$1,975.55 |
|
LIGHT FITTINGS |
5 days |
Mon 9/7/20 |
Fri 9/11/20 |
$1,575.68 |
|
CURTAINS AND SHUTTER |
3 days |
Tue 9/8/20 |
Thu 9/10/20 |
$1,636.60 |
|
TV ANTENA |
3 days |
Tue 9/8/20 |
Thu 9/10/20 |
$250.00 |
|
POLISHING AND FLOOR SANDING |
2 days |
Wed 9/9/20 |
Thu 9/10/20 |
13 |
$657.24 |
METAL FENCING |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
66 |
$2,700.00 |
CONCRETOR EXTERNAL |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
16 |
$5,192.00 |
CONCRETE HARDWARE EXTERNAL |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
82 |
$1,412.00 |
EXTERNAL CONCRETE |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
81 |
$3,098.80 |
CONCRETE SAND EXTERNAL |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
80 |
$562.50 |
CONCRETE MACHINE HIRING |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
70 |
$460.00 |
FINAL FIX CARPENTER |
1 day |
Fri 9/11/20 |
Fri 9/11/20 |
68 |
$404.18 |
HOT WATERING SYSTEM |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$645.00 |
|
SECURITY SCREENS |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$2,902.48 |
|
INSULATION |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$1,498.05 |
|
HOUSE CLEAN |
1 day |
Tue 9/1/20 |
Tue 9/1/20 |
$808.35 |
|
FINAL SITE CLEANING |
1 day |
Mon 9/14/20 |
Mon 9/14/20 |
89 |
$500.00 |
LANDSCAPE |
1 day |
Wed 9/16/20 |
Wed 9/16/20 |
88 |
$3,740.00 |
LANDSCAPE PLANTS |
1 day |
Wed 9/16/20 |
Wed 9/16/20 |
87 |
$2,500.00 |
GARDEN EDGING |
1 day |
Mon 9/14/20 |
Mon 9/14/20 |
86 |
$201.00 |
FLOOR COVERINGS |
3 days |
Wed 9/9/20 |
Fri 9/11/20 |
14 |
$2,475.00 |
FENCING |
3 days |
Wed 9/9/20 |
Fri 9/11/20 |
15 |
$2,875.00 |
CLOTHS HOISTS |
3 days |
Wed 9/9/20 |
Fri 9/11/20 |
17 |
$211.00 |
ESTIMATING |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
100 |
$915.75 |
THEFT AND CONTINGENCY |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
99 |
$1,500.00 |
WINDOW SERVICE |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
98 |
$123.77 |
PLUMBING APPROVAL |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
85 |
$266.20 |
MAINTENANCE |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
84 |
$455.00 |
POWER USAGE |
1 day |
Tue 9/15/20 |
Tue 9/15/20 |
83 |
$160.00 |
From the above table the project activity as per their name and description has been mentioned. In this work schedule the activities has been taken place one by one. In this section, the predecessors have been given with the activity list. The duration of activities also been given where some of them has started early and been completed within a couple of days while some of them are been completed with a few days.
Al-Zwainy, F. M. S., Amer, R., & Khaleel, T. (2016). Reviewing of the simulation models in cost management of the construction projects. Civil Engineering Journal, 2(11), 607-622.
Chitongo, A. M., & Pretorius, L. (2018). Client project time schedule controls-An empirically-based system dynamics conceptual model. South African Journal of Industrial Engineering, 29(1), 169-183.
Didkovskaya, O. V., Mamayeva, O. A., & Ilyina, M. V. (2016). Development of cost engineering system in construction. Procedia Engineering, 153, 131-135.
Gbahabo, P. T., & Ajuwon, O. S. (2017). Effects of project cost overruns and schedule delays in Sub-Saharan Africa. European Journal of Interdisciplinary Studies, 3(2), 46-59.
Guo, Y. T., Yang, S. T., Wang, L., & Luo, S. J. (2016). Project progress measurement under the circumstance of interrupted schedule. Filomat, 30(15), 4037-4048.
Halou, M., Samin, R., & Ahmad, M. (2019). Impacts of change management on risk and cost management of a construction projects. Journal of Project Management, 4(2), 157-164.
Izmailov, A., Korneva, D., & Kozhemiakin, A. (2016). Project management using the buffers of time and resources. Procedia-Social and Behavioral Sciences, 235, 189-197.
Li, X., Xu, J., & Zhang, Q. (2017). Research on construction schedule management based on BIM technology. Procedia engineering, 174, 657-667.
Salem, D., Bakr, A., & El Sayad, Z. (2018). Post-construction stages cost management: Sustainable design approach. Alexandria engineering journal, 57(4), 3429-3435.
Wolken-Möhlmann, G., Bendlin, D., Buschmann, J., & Wiggert, M. (2016). Project schedule assessment with a focus on different input weather data sources. Energy Procedia, 94, 517-522.
Remember, at the center of any academic work, lies clarity and evidence. Should you need further assistance, do look up to our Management Assignment Help
1,212,718Orders
4.9/5Rating
5,063Experts
Turnitin Report
$10.00Proofreading and Editing
$9.00Per PageConsultation with Expert
$35.00Per HourLive Session 1-on-1
$40.00Per 30 min.Quality Check
$25.00Total
FreeGet
500 Words Free
on your assignment today
Get
500 Words Free
on your assignment today
Doing your Assignment with our resources is simple, take Expert assistance to ensure HD Grades. Here you Go....
Min Wordcount should be 2000 Min deadline should be 3 days Min Order Cost will be USD 10 User Type is All Users Coupon can use Multiple